Under Ground Drainage Department


Projects On Hand

Description Project Name – SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work Part A) : Design, Construction, testing and commissioning, of Sewerage Pumping Station at Gokulnagar-Panakhan area for Zone –N2 & other area including all civil works, supply, installation & testing of pumping machineries with all electro mechanical installations with ancillary works wherever necessary with 12 months defect liability period and 2 years of Operation and Maintenance.(EPC Work) Part B): Supplying, Lowering, Jointing, Testing and Commissioning of 450 mm. dia. Rising main from Gokul Nagar Chowk to Pavanchaki work under swrnim jayanti Mukhya Mantri shaheri vikas yojna.(SJMMSVY).
Budget Provision SJMMSVY
Estimated Expense Rs. 8.26 Crores
Contractor Name Sterling Infrastructures Company
Percentage of Work completed 64%
Estimated Date of Work Completion 02nd December, 2016.
Remark Work in Progress

Description Project Name - ICZM Project Integrated Costal Zone Management(World Bank)
Name Of Work Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project. Part - I & Package - I (Zone - A, B, G, H, M).
Budget Provision ICZM
Estimated Expense Rs. 16.38 Crores
Contractor Name M/S Vishwa Infrastructures & Services Pvt. Ltd.
Percentage of Work completed 99.17%
Estimated Date of Work Completion 31-12-2015
Remark Completed

Description Project Name - ICZM Project Integrated Costal Zone Management (World Bank)
Name Of Work Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project. Part - I & Package - II (Zone - K & L).
Budget Provision ICZM
Estimated Expense : Rs. 25.57 (In Crores )
Contractor Name : DineshChandra R. Agrawal Infracon Pvt. Ltd.
Project Start Date : Dt. 30th June, 2011
Percentage of Work completed : 100%
Estimated Date of Work Completion : 31st July, 2014
Remark : Work Completed.

Description Project Name - ICZM Project Integrated Costal Zone Management (World Bank)
Name Of Work Procurement of Super Power High Flow Jetting cum super sucker (Deep Suction) Machine with 2 Nos of Sludge Dump tank and comprehensive Operation & Maintenance contract for 3 years.
Budget Provision ICZM
Estimated Expense : Rs. 2.79 (In crores)
Contractor Name : Kam-Avida Enviro Engineers Pvt. Ltd.
Project Start Date : Dt. 20th September, 2012
Percentage of Work completed : 68%
Estimated Date of Work Completion : 30th September, 2013
Remark : Work Completed & 3 yrs O & M Period Work in Progress
Description Project Name - ICZM Project Integrated Costal Zone Management (World Bank)
Name Of Work Construction of Sewage Pumping Station at Vorana Hazira and Replacement of Pumping Machineries at Kalavad and Gandhinagar Pumping Station.
Budget Provision ICZM
Estimated Expense : Rs. 6.79 ( In Crores)
Contractor Name : Sterling Infrastructures Company
Project Start Date : Dt. 3rd August, 2012
Percentage of Work completed : 100%
Estimated Date of Work Completion : 15th January, 2014
Remark : Work Completed & 2 yrs O & M Period Started.
Description Project Name - ICZM Project Integrated Costal Zone Management (World Bank)
Name Of Work Construction of 70 MLD Sewage Treatment Plant on Design, Build, Testing, Commissioning & Operating the plant for 13 years after initial 2 years O & M.
Budget Provision ICZM
Estimated Expense : Rs. 78.00 (In crores)
Contractor Name : Essar Projects (India) Limited
Project Start Date : Dt. 8th October, 2013
Percentage of Work completed : 97%
Estimated Date of Work Completion : 31st July, 2016
Remark : Work In Progress.
Description Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Zone N - 1.
Budget Provision SJMMSVY
Estimated Expense : Rs. 29.51 (in Crores)
Contractor Name : Phoenix Project Pvt. Ltd.
Project Start Date : 04th March, 2014.
Percentage of Work completed : 77%
Estimated Date of Work Completion : 3rd December, 2016.
Remark : Work In Progress.
Description Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Zone N - 2.
Budget Provision SJMMSVY
Estimated Expense : Rs. 30.46 (In crores)
Contractor Name : Dineshchandra R. Agrawal Inracon Pvt. Ltd.
Project Start Date : Dt. 16th December, 2013.
Percentage of Work completed : 93%
Estimated Date of Work Completion : 16th June, 2016
Remark : Work In Progress.
Description Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Navagam Ghed Area.
Budget Provision SJMMSVY
Estimated Expense : Rs. 29.22 (In Crores)
Contractor Name : Dineshchandra R. Agrawal Inracon Pvt. Ltd.
Project Start Date : Dt. 16th December, 2013.
Percentage of Work completed : 82%
Estimated Date of Work Completion : 15th September, 2016
Remark : Work In Progress.
Description Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work Construction of Navagam Ghed Main Pumping Station.
Budget Provision SJMMSVY
Estimated Expense : Rs. 4.10 (In crores)
Contractor Name : Batliboi Environmental Engineering Limited
Project Start Date : Dt. 03rd May, 2011.
Percentage of Work completed : 97%
Estimated Date of Work Completion : 30th November, 2014
Remark : Work In Progress.
Description Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work 800 - 900 - 1600 M.M. dia Main Trunk Pipe Line Labor Work.
Budget Provision SJMMSVY
Estimated Expense : Rs. 15.17
Contractor Name : Maruti Trading Pvt. Ltd.
Project Start Date : Dt. 25th February, 2013.
Percentage of Work completed : 100%
Estimated Date of Work Completion : 31st July, 2015
Remark : Work Completed.
Description Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work 800 - 900 - 1600 M.M. dia Main Trunk Pipe Line Supply Work.
Budget Provision SJMMSVY
Estimated Expense : Rs. 2.17 (In crores)
Contractor Name : Sterling Infrastructures Company
Project Start Date : Dt. 10th April, 2013.
Percentage of Work completed : 100%
Estimated Date of Work Completion : 16-05-2015.
Remark : Work Completed