Description | Widening and Recarpeting of existing road from Vijay Nagar Jakat Naka (Gyanshakti Circle) |
Budget Provision | SJMMSVY |
Estimated Expense (Rs. in Lacs) | 248.15 |
Contractor Name | Matang Engineers |
Project Start Date | 25/08/2015 |
Percentage of Work Completed | 10% |
Estimated Date of Work Completion | 31/12/2016 |
|
Description | Widening and Asphalt Recarpeting of existing road from Gyan Shakti Circle through Hariya College, Railway Over Bridge and upto Rajkot By Pass Road with 3 No. of RCC Box Culver Cross Drainage work (SJMMSVY 2013 UDP 78) |
Budget Provision | SJMMSVY |
Estimated Expense (Rs. in Lacs) | 641.44 |
Contractor Name | G. V. Sutariya |
Project Start Date | 25/08/2015 |
Percentage of Work Completed | 90% |
Estimated Date of Work Completion | 31/07/2016 |
Remark | Work in Progress. |
|
Description | Construction and Insertion of 1 X 7.50 X 2.67 (Internal Dimension) Precast RCC Box by Pushing technique, RCC Cast in situ Box, Approach portion, & other Miscellaneous Works under broad gauge railway line Jamnagar - Lakhabawal Line at Km 831/2-3, of Westeren Railway, in Jamnagar Municipal Area, Jamnagar. (Under the grant of SJMMSVY & GUDC) |
Budget Provision | GUDC & SJMMSVY |
Estimated Expense (Rs. in Lacs) | 694.32 |
Contractor Name | Nemi Engineering |
Project Start Date | 10/09/2015 |
Percentage of Work Completed | 40% |
Estimated Date of Work Completion | 31/12/2016 |
Remark |
|
Description | PROPOSED CONSTRUCTION OF APPROACHES OF ROB IN LIEU OF LC NO : 197/A , AT KM 827/ 3-4 ON RAJKOT -DWARKA BG LINE IN JAMNAGAR CITY ON BEDI BANDAR ROAD, JAMNAGAR. (Under the Grant of GUDC & SJMMSVY)”. |
Budget Provision | GUDC & SJMMSVY |
Estimated Expense (Rs. in Lacs) | 2014.00 |
Contractor Name | Rachna Construction Co. |
Project Start Date | 12/08/2015 |
Percentage of Work Completed | 25% |
Estimated Date of Work Completion | 28/02/2017 |
Remark | Work In Progress. |
|
Description | Construction of Approaches of ROB in lieu of LC No. 200/A, at km 830/4-5 on Jamnagar – Dwarka BG Line in Jamnagar City on Khambhaliya Road, Jamnagar |
Budget Provision | GUDC & SJMMSVY |
Estimated Expense (Rs. in Lacs) | 3066.00 |
Contractor Name | Rachna Construction Co. |
Project Start Date | 04/03/2014 |
Percentage of Work Completed | 80% |
Estimated Date of Work Completion | 31/07/2016 |
Remark | Work In Progress. |
|
Description | Construction of Fire Quarter, Fire Station, Record Room, Store Room at Jamnagar |
Budget Provision | SJMMSVY |
Estimated Expense (Rs. in Lacs) | 1269.00 Lacs |
Contractor Name | Shanti Construction (G) Pvt. Ltd |
Project Start Date | 13/05/2015 |
Percentage of Work Completed | 95% |
Estimated Date of Work Completion | 12-07-2016 |
Remark | Work In Progress. |
|
Description | CONSERVATION & RESTORATION OF THE LAKHOTA KOTHO IN MIDDLE OF RANMAL LAKE AT JAMNAGAR |
Budget Provision | SJMMSVY |
Estimated Expense (Rs. in Lacs) | 870.55 Lacs |
Contractor Name | AKSHAR SHILP - JAMNAGAR |
Project Start Date | 22/05/2015 |
Percentage of Work Completed | 45% |
Estimated Date of Work Completion | 22-05-2017 |
Remark | Work In Progress. |
|
Description | CONSERVATION, RESTORATION, CONSOLIDATION & REORGANIZATION OF MUSEUM FOR LAKHOTA KOTHO - JAMNAGAR (TENDER FOR REORGANIZATION OF MUSEUM, CITY GALLERY ETC. INTERIOR & FURNISHING WORKS IN TWO BID SYSTEM) |
Budget Provision | (UNDER THE GRANT OF SJMMSVY 2013) |
Estimated Expense (Rs. in Lacs) | 306.49 |
Contractor Name | Akshar Shilp Jamnagar |
Project Start Date | 09-09-2015 |
Percentage of Work Completed | 25% |
Estimated Date of Work Completion | 09-12-2016 |
Remark | Work In Progress. |
|
Description | CONSERVATION, RESTORATION, CONSOLIDATION & REORGANIZATION OF MUSEUM FOR LAKHOTA KOTHO JAMNAGAR (UNDER THE GRANT OF SJMMSVY - 2013 OF THE LAKHOTA KOTHO IN MIDDLE OF RANMAL LAKE AT JAMNAGAR (ELECTRIC WORK SCHEDULE - B FOR LAKHOTA KOTHA & ITS SURROUNDINGS IN TWO BID SYSTEM) |
Budget Provision | (UNDER THE GRANT OF SJMMSVY 2013) |
Estimated Expense (Rs. in Lacs) | 674.10 |
Contractor Name | Accent Engineering Jamnagar |
Project Start Date | 07-10-2015 |
Percentage of Work Completed | 25% |
Estimated Date of Work Completion | 07-12-2016 |
Remark | Work In Progress. |
|