Under Ground Drainage Department


 
Projects On Hand
Project Detail
DescriptionProject Name - Atal Mission for Rejuvenation and Urban Transformation (AMRUT)
Name Of Work

Designing, Providing, Lowering, Laying, Jointing, Testing and Commissioning Sewer Collection Network at Jamnagar Old Fort Area Sewerage System in Jamnagar

Budget Provision

AMRUT Mission

Approved Cost

Rs. 24.58 (In crores)

Expenditure

-

Contractor Name

N P Patel and Company

Project Start Date

24 October, 2017.

Percentage of Work completed

0.50%

Estimated Date of Work Completion

23 October, 2019

Remarks

Work In Progress.

    
DescriptionProject Name - Atal Mission for Rejuvenation and Urban Transformation (AMRUT)
Name Of WorkDesigning, Construction, Testing and commissioning ofSewer Collection Pipe Line Network in Nagarsim & newly merged area inJamnagar Underground Drainage Work Under AMRUT Yojana.
Budget ProvisionAMRUT Mission
Approved CostRs. 15.04 (in Crores)
ExpenditureRs. 5.09 (in Crores)
Contractor NameP C Snehal Construction Private Limited
Project Start Date28 March, 2017.
Percentage of Work completed45%
Estimated Date of Work Completion27 March, 2019.
RemarksWork In Progress.
    
DescriptionProject Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work800 - 900 - 1600 M.M. dia Main Trunk Pipe Line Supply Work.
Budget ProvisionSJMMSVY
Estimated ExpenseRs. 2.17 (In crores)
Contractor NameSterling Infrastructures Company
Project Start DateDt. 10th April, 2013.
Percentage of Work completed100%
Estimated Date of Work Completion16-05-2015.
RemarkWork Completed.
    
DescriptionProject Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of Work800 - 900 - 1600 M.M. dia Main Trunk Pipe Line Labor Work.
Budget ProvisionSJMMSVY
Estimated ExpenseRs. 15.17
Contractor NameMaruti Trading Pvt. Ltd.
Project Start DateDt. 25th February, 2013.
Percentage of Work completed100%
Estimated Date of Work Completion31st July, 2015
RemarkWork Completed
    
DescriptionProject Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of WorkConstruction of Navagam Ghed Main Pumping Station
Budget ProvisionSJMMSVY
Estimated ExpenseRs. 4.10 (In crores)
Contractor NameBatliboi Environmental Engineering Limited
Project Start DateDt. 03rd May, 2011.
Percentage of Work completed97%
Estimated Date of Work Completion30th November, 2014 
RemarkWork In Progress.
    
DescriptionProject Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of WorkConstruction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Navagam Ghed Area.
Budget ProvisionSJMMSVY
Estimated ExpenseRs. 29.22 (In Crores)
Contractor NameDineshchandra R. Agrawal Inracon Pvt. Ltd
Project Start DateDt. 16th December, 2013.
Percentage of Work completed82%
Estimated Date of Work Completion15th September, 2016
RemarkWork In Progress.
    
DescriptionProject Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of WorkConstruction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Zone N - 2.
Budget ProvisionSJMMSVY
Estimated ExpenseRs. 30.46 (In crores)
Contractor NameDineshchandra R. Agrawal Inracon Pvt. Ltd.
Project Start DateDt. 16th December, 2013
Percentage of Work completed93%
Estimated Date of Work Completion16th June, 2016
RemarkWork In Progress.
    
DescriptionProject Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Name Of WorkConstruction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Zone N - 1.
Budget ProvisionSJMMSVY
Estimated ExpenseRs. 29.51 (in Crores)
Contractor NamePhoenix Project Pvt. Ltd.
Project Start Date04th March, 2014.
Percentage of Work completed77%
Estimated Date of Work Completion3rd December, 2016.
RemarkWork In Progress
    
DescriptionProject Name - ICZM Project Integrated Costal Zone Management (World Bank)
Name Of WorkConstruction of 70 MLD Sewage Treatment Plant on Design, Build, Testing, Commissioning & Operating the plant for 13 years after initial 2 years O & M.
Budget ProvisionICZM
Estimated ExpenseRs. 78.00 (In crores)
Contractor NameEssar Projects (India) Limited
Project Start DateDt. 8th October, 2013
Percentage of Work completed97%
Estimated Date of Work Completion31st July, 2016
Remark :Work In Progress.
    
DescriptionProject Name - ICZM Project Integrated Costal Zone Management (World Bank)
Name Of WorkConstruction of Sewage Pumping Station at Vorana Hazira and Replacement of Pumping Machineries at Kalavad and Gandhinagar Pumping Station.
Budget ProvisionICZM
Estimated ExpenseRs. 6.79 ( In Crores)
Contractor NameSterling Infrastructures Company
Project Start DateDt. 3rd August, 2012
Percentage of Work completed100%
Estimated Date of Work Completion15th January, 2014
RemarkWork Completed & 2 yrs O & M Period Started.
    
DescriptionProject Name - ICZM Project Integrated Costal Zone Management (World Bank)
Name Of WorkProcurement of Super Power High Flow Jetting cum super sucker (Deep Suction) Machine with 2 Nos of Sludge Dump tank and comprehensive Operation & Maintenance contract for 3 years.
Budget ProvisionICZM
Estimated ExpenseRs. 2.79 (In crores)
Contractor NameKam-Avida Enviro Engineers Pvt. Ltd.
Project Start DateDt. 20th September, 2012
Percentage of Work completed68%
Estimated Date of Work Completion30th September, 2013
RemarkWork Completed & 3 yrs O & M Period Work in Progress
    
DescriptionProject Name - ICZM Project Integrated Costal Zone Management (World Bank)
Name Of WorkConstruction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project. Part - I & Package - II (Zone - K & L).
Budget ProvisionICZM
Estimated ExpenseRs. 25.57 (In Crores )
Contractor NameDineshChandra R. Agrawal Infracon Pvt. Ltd.
Project Start DateDt. 30th June, 2011
Percentage of Work completed100%
Estimated Date of Work Completion31st July, 2014
RemarkWork Complete
    
DescriptionProject Name - ICZM Project Integrated Costal Zone Management(World Bank)
Name Of WorkConstruction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project. Part - I & Package - I (Zone - A, B, G, H, M).
Budget ProvisionICZM
Estimated ExpenseRs. 16.38 Crores
Contractor NameM/S Vishwa Infrastructures & Services Pvt. Ltd.
Percentage of Work completed99.17%
Estimated Date of Work Completion31-12-2015
RemarkCompleted
    
DescriptionProject Name – SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana
Budget ProvisionSJMMSVY
Estimated ExpenseRs. 8.26 Crores
Contractor NameSterling Infrastructures Company
Percentage of Work completed64%
Estimated Date of Work Completion02nd December, 2016.
RemarkWork in Progress