Description | Project Name - Atal Mission for Rejuvenation and Urban Transformation (AMRUT) |
Name Of Work | Designing, Providing, Lowering, Laying, Jointing, Testing and Commissioning Sewer Collection Network at Jamnagar Old Fort Area Sewerage System in Jamnagar |
Budget Provision | AMRUT Mission |
Approved Cost | Rs. 24.58 (In crores) |
Expenditure | - |
Contractor Name | N P Patel and Company |
Project Start Date | 24 October, 2017. |
Percentage of Work completed | 0.50% |
Estimated Date of Work Completion | 23 October, 2019 |
Remarks | Work In Progress. |
|
Description | Project Name - Atal Mission for Rejuvenation and Urban Transformation (AMRUT) |
Name Of Work | Designing, Construction, Testing and commissioning ofSewer Collection Pipe Line Network in Nagarsim & newly merged area inJamnagar Underground Drainage Work Under AMRUT Yojana. |
Budget Provision | AMRUT Mission |
Approved Cost | Rs. 15.04 (in Crores) |
Expenditure | Rs. 5.09 (in Crores) |
Contractor Name | P C Snehal Construction Private Limited |
Project Start Date | 28 March, 2017. |
Percentage of Work completed | 45% |
Estimated Date of Work Completion | 27 March, 2019. |
Remarks | Work In Progress. |
|
Description | Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana |
Name Of Work | 800 - 900 - 1600 M.M. dia Main Trunk Pipe Line Supply Work. |
Budget Provision | SJMMSVY |
Estimated Expense | Rs. 2.17 (In crores) |
Contractor Name | Sterling Infrastructures Company |
Project Start Date | Dt. 10th April, 2013. |
Percentage of Work completed | 100% |
Estimated Date of Work Completion | 16-05-2015. |
Remark | Work Completed. |
|
Description | Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana |
Name Of Work | 800 - 900 - 1600 M.M. dia Main Trunk Pipe Line Labor Work. |
Budget Provision | SJMMSVY |
Estimated Expense | Rs. 15.17 |
Contractor Name | Maruti Trading Pvt. Ltd. |
Project Start Date | Dt. 25th February, 2013. |
Percentage of Work completed | 100% |
Estimated Date of Work Completion | 31st July, 2015 |
Remark | Work Completed |
|
Description | Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana |
Name Of Work | Construction of Navagam Ghed Main Pumping Station |
Budget Provision | SJMMSVY |
Estimated Expense | Rs. 4.10 (In crores) |
Contractor Name | Batliboi Environmental Engineering Limited |
Project Start Date | Dt. 03rd May, 2011. |
Percentage of Work completed | 97% |
Estimated Date of Work Completion | 30th November, 2014 |
Remark | Work In Progress. |
|
Description | Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana |
Name Of Work | Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Navagam Ghed Area. |
Budget Provision | SJMMSVY |
Estimated Expense | Rs. 29.22 (In Crores) |
Contractor Name | Dineshchandra R. Agrawal Inracon Pvt. Ltd |
Project Start Date | Dt. 16th December, 2013. |
Percentage of Work completed | 82% |
Estimated Date of Work Completion | 15th September, 2016 |
Remark | Work In Progress. |
|
Description | Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana |
Name Of Work | Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Zone N - 2. |
Budget Provision | SJMMSVY |
Estimated Expense | Rs. 30.46 (In crores) |
Contractor Name | Dineshchandra R. Agrawal Inracon Pvt. Ltd. |
Project Start Date | Dt. 16th December, 2013 |
Percentage of Work completed | 93% |
Estimated Date of Work Completion | 16th June, 2016 |
Remark | Work In Progress. |
|
Description | Project Name - SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana |
Name Of Work | Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project Zone N - 1. |
Budget Provision | SJMMSVY |
Estimated Expense | Rs. 29.51 (in Crores) |
Contractor Name | Phoenix Project Pvt. Ltd. |
Project Start Date | 04th March, 2014. |
Percentage of Work completed | 77% |
Estimated Date of Work Completion | 3rd December, 2016. |
Remark | Work In Progress |
|
Description | Project Name - ICZM Project Integrated Costal Zone Management (World Bank) |
Name Of Work | Construction of 70 MLD Sewage Treatment Plant on Design, Build, Testing, Commissioning & Operating the plant for 13 years after initial 2 years O & M. |
Budget Provision | ICZM |
Estimated Expense | Rs. 78.00 (In crores) |
Contractor Name | Essar Projects (India) Limited |
Project Start Date | Dt. 8th October, 2013 |
Percentage of Work completed | 97% |
Estimated Date of Work Completion | 31st July, 2016 |
Remark : | Work In Progress. |
|
Description | Project Name - ICZM Project Integrated Costal Zone Management (World Bank) |
Name Of Work | Construction of Sewage Pumping Station at Vorana Hazira and Replacement of Pumping Machineries at Kalavad and Gandhinagar Pumping Station. |
Budget Provision | ICZM |
Estimated Expense | Rs. 6.79 ( In Crores) |
Contractor Name | Sterling Infrastructures Company |
Project Start Date | Dt. 3rd August, 2012 |
Percentage of Work completed | 100% |
Estimated Date of Work Completion | 15th January, 2014 |
Remark | Work Completed & 2 yrs O & M Period Started. |
|
Description | Project Name - ICZM Project Integrated Costal Zone Management (World Bank) |
Name Of Work | Procurement of Super Power High Flow Jetting cum super sucker (Deep Suction) Machine with 2 Nos of Sludge Dump tank and comprehensive Operation & Maintenance contract for 3 years. |
Budget Provision | ICZM |
Estimated Expense | Rs. 2.79 (In crores) |
Contractor Name | Kam-Avida Enviro Engineers Pvt. Ltd. |
Project Start Date | Dt. 20th September, 2012 |
Percentage of Work completed | 68% |
Estimated Date of Work Completion | 30th September, 2013 |
Remark | Work Completed & 3 yrs O & M Period Work in Progress |
|
Description | Project Name - ICZM Project Integrated Costal Zone Management (World Bank) |
Name Of Work | Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project. Part - I & Package - II (Zone - K & L). |
Budget Provision | ICZM |
Estimated Expense | Rs. 25.57 (In Crores ) |
Contractor Name | DineshChandra R. Agrawal Infracon Pvt. Ltd. |
Project Start Date | Dt. 30th June, 2011 |
Percentage of Work completed | 100% |
Estimated Date of Work Completion | 31st July, 2014 |
Remark | Work Complete |
|
Description | Project Name - ICZM Project Integrated Costal Zone Management(World Bank) |
Name Of Work | Construction Under Ground Sewer Collection System & House Connection Network for Jamnagar Under Ground Sewerage Project. Part - I & Package - I (Zone - A, B, G, H, M). |
Budget Provision | ICZM |
Estimated Expense | Rs. 16.38 Crores |
Contractor Name | M/S Vishwa Infrastructures & Services Pvt. Ltd. |
Percentage of Work completed | 99.17% |
Estimated Date of Work Completion | 31-12-2015 |
Remark | Completed |
|
Description | Project Name – SJMMSVY Swarnim Jayanti Mukhi Mantrishree Sheri Vikas Yojana |
Budget Provision | SJMMSVY |
Estimated Expense | Rs. 8.26 Crores |
Contractor Name | Sterling Infrastructures Company |
Percentage of Work completed | 64% |
Estimated Date of Work Completion | 02nd December, 2016. |
Remark | Work in Progress |
|