Providing, Supplying,Lowering, Laying,Jointing ,Fixing and Testing of DI K-7 Pipeline for Distribution Network of Jamnagar Water Supply Scheme (for newly merged outer growth of Gokulnagar ,Mahaprabhuji,Lalpur road Gyanganga Zone)
| Budget Provision
|
SJMMSVY Grant
|
| Estimated Expense(Rs. in Lacs)
|
24,60,38,009=10
|
| Contractor Name
|
P.C.Snehal Construction Co.
|
| Project Start Date
|
15-09-15
|
| Percentage of Work Completed |
25% |
| Estimated Date of Work Completion |
14-03-17 |
| Remark |
- |